The Kings School, Gloucester

Full Refurbishment of Science Laboratory

The Kings School, Gloucester

A belated thanks for all you and Klick did on the refurbishment to our Chemistry Lab over Easter. It looks great and has given the department much more kudos with the students. They are still, half a term on, excited about doing science in there. I really appreciated your personal attention and time in this project and that really helped us find the perfect solution for what we wanted to end up with.

Andy Moore – Head of Science, The King’s School, Gloucester

PROJECT BRIEF

The school opted to take advantage of our pre summer discount in order to maximise their budget. However it was paramount that the project was completed whilst the students were absent during school holidays.

 

The work was scheduled to start at 1pm as the students left for the Easter holidays. The Klick site team moved in immediately and worked through the holidays completing the project in under 3 weeks, in time for the start of term.

Klick worked with the school to maximise the budget. One existing fume cupboard was upgraded, the existing ceiling was painted and the school kept the existing blinds.

 

The chemistry department opted for a curved cranked design, which met their design brief of creating ‘wow factor’ to inspire the students whilst still allowing all the students to comfortably face the front.

 

They thought the finished lab was the ‘perfect solution’.

PROJECT DETAILS

  • Free comprehensive design and consultation service
  • 2D & 3D CAD drawings provided
  • Full project management service
  • Removal of existing furniture and redundant services
  • Channel floor to teacher’s bench for interactive services conduit
  • Remove 2 existing radiators and install 3 new radiators
  • One existing fume cupboard removed/one upgraded
  • Installation of new electrical and plumbing services including new distribution board & circuit breakers
  • Supply and installation of furniture
  • Decoration, lighting and flooring renewed
  • Gas safety proving systems installed with C02 monitors
  • Final connections, commissioning and certification of all works

Contact us for a free no obligation quote

 

Project Description:

Full Refurbishment of Science Laboratory

Value:

£38k

Client:

The King’s School, Gloucester

Duration Of Work

Under 3 Weeks

Category
Refurbishment