Culcheth High School, Cheshire

Science Laboratory Refurbishments

Culcheth High School, Cheshire

Following the tender process to 6 companies I felt confident that Klick’s package fully met the brief and they were the only company to include everything specified for the two science laboratory refurbishments. Their designers were helpful from the start, changing the drawings and refining the design until the science department were happy. The furniture was installed during term time with some of the initial noisy building work completed out of school hours. The whole project was finished to a very high standard and I had no hesitation in asking them to complete a further lab 3 years later.

Andrew Parker – Facilities Manager, Culcheth High School, Cheshire

PROJECT BRIEF

The school was rebuilt in 2010 to include 7 new science labs. However over time it became clear that science provision at the school needed to be increased. The brief was to convert existing classrooms into flexible science laboratories to co-ordinate with the original labs.

THE RESULTS

Klick were delighted to be appointed to carry out the inital conversion of two classrooms into science laboratories. Our design team worked closely with the school to develop a flexible bollard layout to suit the requirements of the science teaching staff.

The school opted to have the project completed during term time in order to take advantage of our discounted rate. Klick’s refurbishment team started the initial strip out whilst the school was closed but the majority of the work was scheduled during the school day, with minimal disruption. The school were delighted with the first two labs and asked Klick to convert a third lab three years later. This room has a combination of short peninsulas and loose tables allowing for the workspace to be reconfigured to accomodate group participation.

PROJECT DETAILS

  • Free comprehensive design and consultation service
  • 2D & 3D CAD drawings provided
  • Full project management service
  • Removal of existing furniture, partition wall and redundant services
  • Channelling of floor
  • Construction of new partition walls & installation of new doorways
  • Installation of new plumbing and electrical services
  • Provision for interactive services
  • Supply and installation of furniture
  • Suspended ceiling altered
  • Decoration, lighting and flooring renewed
  • Gas safety proving systems installed with C02 monitors
  • Final connections, commissioning and certification of all works.

Contact us for a free no obligation quote

 

Project Description:

Two phase conversion to provide 3 science laboratories.

Value:

£98k

Client:

Culcheth High School, Cheshire

Duration Of Work:

Phase 1 - 6 weeks Phase 2 - 4 weeks

Category
Refurbishment, Science
Tags
Conversion, Flexible Layout, Refurbishment, Science lab, Secondary School, Term-time discount